Pursuit's Take
Costs substantially increased and schedules were delayed for Department of Veterans Affairs’ (VA) largest medical-center construction projects in Denver, Colorado; Las Vegas, Nevada; New Orleans, Louisiana; and Orlando, Florida. As of November 2012, the cost increases for these projects ranged from 59 percent to 144 percent, with a total cost increase of nearly $1.5 billion and an average increase of approximately $366 million. The delays for these projects range from 14 to 74 months, resulting in an average delay of 35 months per project.
Although VA has taken some actions to address problems managing major construction projects, the agency has opportunities for further improvement.
Media Coverage
Health Facilities Management: VA learns hard lessons from hospital projects